47
Total Applications
Mobile Tower Application
Documents and Checklists:
- Copy of relevant license or Infrastructure Provider Registration Certificate from
DoT.
- Copy of structural stability certificate for Roof-Top Towers.
- Copy of the type test certificate issued by Automotive Research Association of India(ARAI)
or any other authorized Agency to the manufacturer of the Disel Generator(DG) Sets.
- Copy of clearance from Fire Safety Department,if applicable.
- Copy of clearance from State Environment & Forest Department,If applicable.
- Drawing of the tower along with specifications of foundations and design parameters
- Indemnity Bond ( Original ) to take care of any loss or injury to accident caused
by the tower.
- Three copies of Location Plan,Site Plan,Elevation Plan and Structure plan.
- Copy of NOC from building/land owner or Authorised Personnel.
- Route plan along with GIS Map only for laying OFC.
- NOC from NHAI,ASi,Airport Authority if required.
- Other documents if any prescribed under this policy.
- Any other certificated/NOC required by the authority from time to time.
|
Sl#.
|
Particulars
|
Urban Areas(Rs)
|
Rural Areas(Rs)
|
|
1
|
One time permission charges for establishment of Telecom Towers(GBT/RTT)
|
10,000
|
5,000
|
|
2
|
Land usage charges for ground base Tower for 3 years(applicable for Govt. land only)
GBM-15*15
GBT-40*40
*Municipal Corporation/Municipality Council Other ULBs(NAC)
|
200 per sq. ft
100 per sq. ft
|
No Charge
|
|
3
|
One time roof usage charges for Roof Top Towers, 10*10 for 3 years(Applicable
foe Govt. buildings only)
*Municipal Corporation/Municipality Council Other ULBs(NAC)
|
300 per sq. ft
200 per sq. ft
|
200 per sq. ft
|
Note : Usage charges can
be calculated on prorate basis as per the area used. These fees can be revised from
time to time by the Nodal Department.